Project:
Lincoln Executive Airport Closure of Runway 16/34
Scope:
Over four phases of construction trench and directional bore new electrical and lighting ductbanks. Remove existing in-pavement and shoulder lighting. Core to install new base cans for new in-pavement and shoulder lighting. Furnish and install new runway and taxiway signs. Extremely fast paced schedule and coordination with General Contractor.
Location:
Sacramento, CA
Owner:
County of Sacramento
GC:
McGuire Hester